1 | June, 2013 | Dec. 2013 | 6 Months 2013-14 | 07/NHAI/PIU-RUPC/273 Dt. 27.06.2013 National Highway Authority of India Special Repair to Rampur-Kathgodam section of NH-87 (new no. 9 & 109) for safe operation of project Highway during Development Period
| Prime Contractor |
2 | Mar. 2013 | June, 2013 | June, 2013 | 16/SE-04/13 Dt. 23.03.2013 Executive Engineer Con. Division PWD Haldwani Reconstruction & Improvement of Deverampur to Century Paper Mill Motor Road under Lalkuan Constituency
| Prime Contractor |
3 | Jan. 2013 | Jan. 2013 | 6 Months 2013-14 | 08/S.E.-04/13 Dt. 31.01.2013 Executive Engineer, Construction Division, PWD, Haldwani Reconstruction work from Coltax to Damuwadunga Panchakki to ITI crossing in Haldwani city of Nainital District Km. 1.900 to 5.500 | Prime Contractor |
4 | June, 2012 | June, 2012 | 1 Year 2012-13 | 13/PTN/SIDCUL/12-13Managing Director, SIDCUL, Pantnagar Reconstruction of Roads and Allied Civil works in Phase-I, Package-II at IIE Pantnagar | Prime Contractor |
5 | Aug. 2012 | Mar. 2013 | 7 Months 2012-13
| 31/SE-NH/2012-13 Dt. 29.08.2012 Executive Engineer NH Division P.W.D. Haldwani Nainital P.R. 2012-13 work with BM and SDBC in NH-74 from Km. 212.00 to 232.00
| Prime Contractor |
6 | Aug. 2012 | Feb. 2013 | 6 Months 2012-13 | 32/SE-NH-2012-13 Dt. 29.08.2012 Executive Engineer NH Circle PWD Haldwani P.R. work 2012-13 with SDBC in Km. 79.00 to 84.00 of NH-87 | Prime Contractor |
7 | June, 2012 | Jul. 2012 | 2 Months 2012-13 | 02/SE-02/2012-13 Dt. 01.06.2012 Executive Engineer Construction Division PWD Ramnagar (Nainital Work with SDBC in a) Keshovala Bannakhera Bailpadav Motor Road km. 14,15 and 16b) Kaladungi Kotabagh Bailpadav Motor Road km. 6,7,17,18,19 and 25 c) Choe Jagannathpur Motor Road km. 3, 4 and 5 | Prime Contractor |
8 | June, 2012 | June, 2012 | 2 Months 2012-13 | 03/SE-02/2012-13 Dt. 04.06.2012 Executive Engineer Construction Division PWD Ramnagar (Nainital) Work with SDBC in a) Tanda Aampokhra Motor Road km. 1 & 2b) Ramnagar Ring Road km. 1,2,16,17,18 and 19
| Prime Contractor |
9 | Oct. 2011 | Mar. 2012 | 5 Months 2011-12
| 63/EE Dt.14.10.2011 Executive Engineer Con. Division PWD Haldwani Work with SDBC in Haldwani Uproad km. 7,8 and 9 and Bamori Bithoriya Dvamunga Road km. 1,2 and 3 | Prime Contractor |
10 | Oct. 2011 | Mar. 2012 | 5 Months 2011-12 | 62/EE Dt.14.10.2011Executive Engineer Con. Division PWD Haldwani Work with SDBC in Haldwani Rudrapur Motor Road from km. 18 to 20 and Devarampur Motahaldu Road | Prime Contractor |
11 | Oct. 2011 | Mar. 2012 | 5 Months 2011-12 | 61/EE Dt.14.10.2011 Executive Engineer Con. Division PWD Haldwani Work with SDBC in Ramnagar-Kaladungi Haldwani Kathgodam Chorgaliya Sitarganj Bizti Road km. 27 and 28 | Prime Contractor |
12 | June, 2012 | June, 2012 | 2 Months 2012-13 | 03/SE-02/2012-13 Dt. 04.06.2012 Executive Engineer Construction Division PWD Ramnagar (Nainital) Work with SDBC in a) Tanda Aampokhra Motor Road km. 1 & 2b) Ramnagar Ring Road km. 1,2,16,17,18 and 19
| Prime Contractor |
13 | Dec. 2011 | Mar. 2012 | 5 Months 2011-12
| 09/SE-04/2011 Dt. 23.12.2011 Executive Engineer, P. D. P.W.D. Rudrapur U.S.Nagar Work with SDBC in Nagla Kichha from km. 13 to 15 under 13th Finance | Prime Contractor |
14 | Dec. 2011 | Mar. 2012 | 5 Months 2011-12 | 07/SE-04/2011 Dt. 23.12.2011 Executive Engineer Con. Division PWD Khatima Work with SDBC in Khatima Majhola SH-04 km. 7, 8, and 9 | Prime Contractor |
13 | Dec. 2011 | Mar. 2012 | 3 Months 2011-12 | 08/SE-04/2011 Dt. 23.12.2011 Executive Engineer Con. Division PWD Khatima SDBC work in Sitarganj Bazar Bhag from km. 1,2 and 3 and Khempur Matiha Bizti Road from km. 2 | Prime Contractor |
14 | Dec. 2011 | Mar. 2012 | 3 Months 2011-12
| 93/EE Dt. 21.12.11 Executive Engineer, P. D. P.W.D. Rudrapur U.S.Nagar SDBC Work in Gadarpur Balramnagar Saidliganj Road Under 13th Finance Commission | Prime Contractor |
15 | Oct. 2011 | Nov. 2011 | 1 Month 2011-12 | 04/SE-NH/2011-12 Dt. 17.10.11 Executive Engineer NH Circle P.W.D. Haldwani Nainital FDR work in NH-74 from km. 221 to 229 and 230 to 232 | |
12 | Mar. 2011 | Mar. 2011 | 1Month 2011-12 | 36/SE-NH-2010-11 Dt. 21.03.11 Executive Engineer NH Circle PWD Haldwani F.D.R. (2010-11) work with S.D.B.C. in Km. 84.00 to 91.00 of NH-87 (Rampur-Nainital motor Road) | |
16 | Mar. 2011 | Apr. 2011 | 1 Month 2011-12
| 08/SE-04/2011Dt. 24.03.2011 Executive Engineer, Construction Division, PWD, Kashipur F.D.R. (2010-11) work with SDBC in km. 56,60,61,62 and 63 of Nainital Kaladungi Baazpur Doraha road | |
16 | Mar. 2011 | Jun. 2011 | 3 Months 2011-12
| 07/SE-04 Dt. 08.03.11 Executive Engineer, Provincial Division P.W.D. Rudrapur Udham Singh NagarF.D.R. (2010-11) work with SDBC in Rudrapur-Haldwani (SH-05) from km.01 to 07 | |